From fruit juice production in Spain to water bottling in Denmark

The challenge
A global food & beverage producer required the full relocation of a large and highly complex aseptic bottling and filling line. The project involved dismantling an operational production line in Seville (Spain), transporting it to long-term storage, and rebuilding it at a new production site in Denmark.
The challenge was multifaceted: strict hygienic requirements due to the aseptic nature of the line, oversized and exceptional transport dimensions, tight on-site timelines, and a long-term, phased project planning across multiple countries.
The solution & execution
Gerritsen Group delivered a fully managed, end-to-end solution — from engineering and dismantling to transport, storage and future reinstallation. Key phases of execution:
- Lift & shift operations for oversized components, including exceptional loads up to 5 meters high
- Custom packaging tailored to aseptic and long-term storage requirements
- Coordinated logistics involving 48 truckloads, including 8 exceptional transports
- Secure warehouse storage for a minimum of one year at Gerritsen Group facilities
- Future relocation and rebuild in Denmark, including recommissioning and recertification of the aseptic line
All dismantling activities were completed within a 6-week on-site window, fully packaged, loaded and transported according to plan.


The result
The complete aseptic production line was safely dismantled, preserved and stored without compromising quality or certification requirements. The project ensured full value retention of a highly specialised production asset and enabled a smooth transition to its next lifecycle phase.
After relocation to Denmark, the line will be rebuilt and recommissioned for water bottling, including full cleaning, re-flushing and recertification according to local regulations. The rebuild phase is scheduled to take approximately 10 weeks, following a long-term planning horizon of 6–12 months.
“The complexity of this relocation required absolute precision, flexibility and trust. Gerritsen Group managed every phase with full control and transparency — from dismantling to storage and future reinstallation.”
– Plant Manager
2 months
Project execution
6 weeks
On-site dismantling
48 truckloads
Shipped & relocated
5m x 4.8m x 12m
(h*w*l) max size loads
100%
Regulatory compliance
get in touch
From complex relocation to future-ready production
This project demonstrates how Gerritsen Group manages large-scale, high-risk industrial relocations with full control over engineering, safety, logistics and long-term planning. Even the most complex aseptic systems remain fully operational and compliant throughout their transition.